Showing posts with label birding. Show all posts
Showing posts with label birding. Show all posts

Friday, January 4, 2019

New Power Lines will not be near Celery Fields

FPL has made its decision on the route of the new transmission lines that will support growth in East Sarasota County, and it's the choice preferred by the communities near the Celery Fields, Sarasota Audubon, and the Fresh Start Initiative -- the route along Clark Road:

FPL Power line route along Clark Rd (click image to enlarge)

Celery Fields advocates and residents had expressed concern at an optional route that would have taken the tall power lines along Palmer Blvd and Apex Rd. near the birding, wildlife and recreation area. Here is the communication from FPL manager Rae Dowling:
After an extensive route selection study by the project team, that included feedback from a diverse Community Advisory Panel, an open house meeting, and meetings with neighborhood groups and community leaders, I’m writing to let you know that Florida Power & Light Company (FPL) has selected its preferred route for the proposed Bobwhite-Howard 138 kV transmission line. On behalf of the entire project team, I want to thank you for your participation in our Community Advisory Panel and for the time you invested providing your perspectives for us to consider in our study.  Having the perspective of our customer’s voice in important to us and we truly value your contribution to this important project. The preferred route, which is included in the attachment to this email, follows along almost the entire 13-mile length of existing FPL transmission and distribution lines, a siting criteria consistently endorsed by our customers. Route surveying work will begin on this project this month.  If you have any questions, please contact myself at the numbers below or Daniel Hronec, P.E., Project Manager at (561) 904-3638 or by email at Daniel.Hronec@FPL.com. Thank you. 

Monday, December 31, 2018

For a happier new year for the Celery Fields

Chuck Behrmann's photos at the Celery Fields speak eloquently to the special nature of Sarasota's unique bird sanctuary. The pristine protection it affords over 226 species of birds was not the result of some government plan.

Wise governmental stewardship would acknowledge Nature's gift and do everything to protect it from harsh or incompatible development. 

Sandhill Crane preening at the Celery Fields wetlands - Chuck Behrmann.
Good stewards would make sure nearby public lands are not used in a way that would impair the quality of the land, air, water, and wildlife. Sensible stewards would give this precious area an adequate buffer zone, sufficient parking, and healthy options for nearby public properties. They would use Critical Area Planning to develop a suitable vision in concert with the community




Let's work to make this a truly happy New Year for all.









photos courtesy of the Celery Fields group or from this blog.

Sunday, December 23, 2018

A new plan for the Celery Fields

Nowadays, mammoth condo and apartment communities are popping up all around the animal sanctuary and the nearby Celery Fields, one of the last remaining undeveloped green spaces in Sarasota County. Herald Tribune, 12.22.18.
Celery Fields, Sarasota

To the Board of Sarasota County Commissioners:
A "Critical Area Plan" (CAP) is a technical tool -- an innovation first developed by Sarasota County planning years ago. According to one of the original planners who developed and implemented CAPs over many years, the purpose of establishing a boundary for a CAP project is to insure that all the important changes a proposed development will bring to a specific area are addressed.*
As a tool for gauging compatibility, clearly the CAP boundary is not intended to encompass just the area of the project. That would not make sense.
When the Fruitville Initiative was designed, the boundaries of the CAP benefited from public input, solicited by the County.
On Sept. 12, 2018, the Board of Sarasota County Commissioners decided it was time to revisit the Critical Area Plan (CAP) for the Quad parcels near the Celery Fields in light of the current context and realities. A discussion item on this is scheduled for Jan. 29, 2019 (time to be determined).



This should provide a long overdue opportunity to envision what is possible at the Celery Fields area, considering the mismatch between old plans from 1983 and the new reality of a world-famous birding destination in the area.


Before starting the CAP process, the BCC will first need to approve the boundaries (i.e. aerial extent) and criteria (plan tasks) at a public hearing.
When Restaurant Depot’s giant warehouse proposal came before this board two years ago, their Critical Area Plan was contrived to coincide with the boundaries of its own parcel. That is to say: the impacts of the giant warehouse upon the Celery Fields and other surrounding parcels were explicitly ignored by the very planning tool that's supposed to take those impacts into account.

In advance of setting CAP boundaries and criteria for the Celery Fields, the defined process requires staff to proactively conduct public meeting(s) to solicit public input on the boundaries and criteria, much as was done at this stage of the Fruitville Initiative.

Given the success of the Audubon Nature Center, the expansion of the Big Cat Habitat, and the undeniable need for more parking and complementary facilities for the tens of thousands of birders, recreationalists and eco-tourists who flock to the Celery Fields each year, it is clearly time for the County to re-envision the entire Celery Fields Area to address its current uses, context and future needs for the people of Sarasota County.
The Fresh Start Initiative

*Sarasota News Leader






Friday, September 7, 2018

Recognition of the "national caliber" of the Celery Fields

In view of the brand new Lambert Advisory report recommending industrial rezoning for one of the Quad Parcels -- precisely the issue that caused a major outcry last year when James Gabbert and Restaurant Depot proposed to put industrial installations on parcels #2 and #3 -- it's helpful to look at what the County's own staff has said about the Celery Fields area:

"Celery Fields is a national caliber example of how recreation, stormwater management and conservation strategies can be leveraged to achieve multiple environmental and recreational benefits, including becoming an international birding destination." Sarasota County Parks 2016 Master Plan, p. 7.

+=========+

"Trends in resource-based recreation indicate that the public seeks nature-based education and programming at nature centers. The County might . . . consider a comprehensive assessment of nature centers at multiple locations . . .. This could be tied in with the existing facilities . . . and Sarasota Audubon Nature Center at Celery Fields." Sarasota County Parks 2016 Master Plan, p. 102.



+=========+

In 2012, the County granted a ground lease to The Sarasota Audubon Society lease in recognition of the significance of the Celery Fields. In the document the County states:
"In addition to its role in the treatment and storage of stormwater, the Celery Fields serves as an important habitat and food source to many species of animals and birds . . ." Sarasota County Ground Lease Agreement with The Sarasota Audubon Society, Inc., 2012.


+=========+

Letter of 2.22.17 from Sarasota Audubon Society to Commissioner Al Maio recommending denial of industrial rezoning of the Quad Parcels last year. "A phenomenal number" of federal and state listed birds have been found at the Celery Fields, whose nesting and feeding would be "at risk."

Audubon recommended county create "an advisory group of affected citizen stakeholders to work with county staff in determining a land use suitable . . ."

The full Audubon report includes a Celery Fields species checklist and statistics on tourist visits.


                                                        +=========+

The Lambert Advisory Report of August 2018 notes the existing zoning for the Quad Parcels: "All commercial and industrial development is prohibited." 

It's a full circle -- in view of the changes to the area -- specifically the Celery Fields birding and recreation area -- what possible justification can there be for rezoning these parcels for industry?





Sunday, February 18, 2018

A recent morning at the Celery Fields



Yesterday morning at the Celery Fields, it was quiet - no highway noise, no copters or trucks. Why would the County be ok with introducing more industrial uses into this sanctuary?

The grass still had dew on it. Far off, a single kayaker was barely a dot on the lake's still surface. A tall fellow was walking up and down the Mound with a substantial backpack and hiking poles. I asked if he were preparing for a trek of some kind. Not right now, he said. Rather it's exercise he takes because he brings groups to the Celery Fields to train for long trail hikes.

"Where would you go if this mound didn't exist?" I asked him. "North Georgia," he said, adding that North Florida's rolling hills weren't steep enough for such training.

The mound is unique in many ways. It affords a wide angle view of clear open space. Look down, often you see birds in flight beneath you. Do our elected officials really want visitors who come for the birds and the beauty to look at heavy trucks, demolition waste, giant warehouses or other industry?

 == Tom Matrullo


Caracara at the Celery Fields - by Chuck Behrmann